From enquiry to handover — in writing.
Seven stages, six ways to contract, and a payment schedule you can see before you sign. No stage starts on a verbal instruction.
Seven stages. One programme.
We can take the whole chain or a single stage. Either way, the sequence is planned before mobilisation, and the interface with your team is written down.
Survey
Roof or land, access, shading, structure, grid and load.
Design
Layout, yield, structural and electrical design, grid interface.
Supply
Specification, factory audit, pre-shipment inspection.
Logistics
Packing, shipping documents, customs coordination.
Construct
Mounting, modules, DC/AC, communications, safety systems.
Energise
Testing, commissioning, monitoring and grid acceptance.
Operate
Inspection, cleaning, spares, remote monitoring, training.
Six ways to work with us.
Most first projects start as supply-only or supply-and-install, then grow into full EPC. The contract is sized to the scope you actually want.
| Model | You provide | We provide | Suits |
|---|---|---|---|
| Design only | Site data, consumption, local grid rules. | Layout, structural and electrical design, BoM, yield model. | Owners with a local installer already selected. |
| Supply only | Approved design and BoM. | Equipment, inspection, documents, delivery to port or site. | EPCs and installers who buy their own materials. |
| Design + supply | Site access and approvals. | Full design package plus equipment and logistics. | Owners using a local installation contractor. |
| Supply + install | Site access, permits, local labour support as agreed. | Materials, our supervision crew, installation, commissioning. | The most common first overseas model. |
| Full EPC | Land or roof rights, permits, grid application, finance. | Design, supply, construction, commissioning, handover pack. | Owners who want one interface and one price. |
| EPC + O&M | Site access and agreed reporting interface. | Everything in EPC, plus inspection, cleaning, fault response and monitoring. | Assets without a local O&M team. |
Labour-only installation for a local EPC is also possible, quoted per kW or per day. Ask if that is what you need.
What is actually in the contract.
We use a fixed-price contract with annexes, not a letter of intent followed by arguments. Every annex has an owner, a number and a date.
- Scope & drawings annex. What is built, what is excluded, and the drawing revision the price is based on.
- Bill of materials. Make, model, quantity and datasheet for every line.
- Programme & milestones. Start, delivery, commissioning and acceptance dates with dependencies.
- Price & payment schedule. Fixed price, currency, milestone payments, retention and release conditions.
- Warranty & defects liability. Equipment warranty passed through; workmanship period stated in months.
- Change orders, HSE, acceptance and dispute resolution. All written, all signed, all before work starts.
Templates available
We can start from our standard template or work under yours if it is balanced. Ask for the current set:
- Supply contract — Incoterms 2020, inspection, title and risk
- Installation contract — measured scope, site conditions, HSE
- Full EPC contract — design, supply, install, commissioning
- O&M agreement — service levels, response times, reporting
Payment milestones, before you sign.
Payment is released against documents and completed work, not against promises. The percentages below are our standard; they can be adjusted with the scope and the country risk.
Equipment supply (T/T)
| Milestone | Share | Released against |
|---|---|---|
| Order confirmation | 30% | Signed contract and factory order placed. |
| Before shipment | 60% | Pre-shipment inspection report, packing list, copy B/L. |
| After arrival | 10% | Site or port acceptance of the delivered goods. |
Installation / full EPC
| Milestone | Share | Released against |
|---|---|---|
| Mobilisation | 20% | Contract signed, site access and permits confirmed. |
| Delivery to site | 50% | Equipment delivered and accepted, progress report signed. |
| Commissioning | 25% | System energised, test records and as-builts issued. |
| Retention | 5% | Released after the defects liability period, typically 12 months. |
What happens next, and who does it.
You get a named project manager and a single email thread. The sequence below is the standard path; dates are fixed at kickoff against your site.
- 01
Kickoff and document freeze
Scope, drawing revision, BoM and programme are frozen. Your contact and ours are named, with a weekly call slot.
Output: signed kickoff record - 02
Design and approvals
Layout, structural and electrical drawings issued for your approval. Local permits and grid application run in parallel on your side.
Output: approved drawing set - 03
Factory order and inspection
Purchase orders placed, hold points agreed, pre-shipment inspection witnessed or reported with photos.
Output: PSI report and certificates - 04
Shipping and customs
Consolidated shipment, documents issued, destination clearance coordinated with your broker.
Output: B/L, CO, insurance, packing list - 05
Mobilisation and installation
Crew, tools and materials on site. Daily progress photos, weekly report, safety induction completed.
Output: weekly progress reports - 06
Commissioning and handover
Testing, monitoring setup, operator training and the handover pack. Defects liability starts at acceptance.
Output: commissioning report, as-builts, warranty pack
What we need from you before mobilisation.
These are the items that most often delay a start. We check them at kickoff and confirm them again one week before the crew travels.
| Item | Why it matters | Owner |
|---|---|---|
| Site access and laydown area | Crane and truck access, secure storage for modules and steel. | You |
| Power and water | Tools, testing and concrete if foundations are in scope. | You |
| Permits and grid application | Installation cannot be energised without them. | You, with our technical inputs |
| Local labour and visas | Some countries require a local hiring ratio; we plan the crew mix accordingly. | Shared |
| HSE induction and site rules | Our crew works to your site rules and our own safety plan. | You |
| Storage and accommodation | Remote sites need secure container storage and crew lodging. | Shared |
| Single point of contact | One person who can approve drawings and access without a committee. | You |
Before you ask.
Who stamps the drawings?
Design is issued and stamped by our partner design institutes in China. For local permits, the drawings may need review or re-stamping by a licensed engineer in your country; we prepare the package so that review is straightforward, and we can work with your local engineer.
Can I buy only the materials?
Yes. Send your approved BoM and we price it as supply-only, delivered FOB, CIF, DAP or DDP depending on what your customs setup allows.
What warranty do I get?
Equipment warranty is passed through from the manufacturer, typically 10–12 years product and 25–30 years performance for modules, and 5–10 years for inverters. Workmanship is warranted by Kunran for a stated period, typically 12–24 months. Exact terms are written into the contract, not assumed.
Who handles customs and duties?
We can quote DAP or DDP, but DDP requires a local entity or a trusted broker in your country. On first projects we usually recommend CIF or DAP with your broker clearing, so responsibility is clear on both sides.
Do you provide financing?
No. We can introduce you to banks and export credit insurers, but we do not lend and we do not take equity in projects.
What if you have never worked in my country?
Then we say so. For a first project in a new country we usually start with supply, or supply plus a supervision crew working alongside a licensed local installer. That keeps the regulatory risk with the party that holds the licence while you test how we work.
Can I visit the factory or witness inspection?
Yes. Factory visits and pre-shipment inspection can be arranged, and a third party such as BV or SGS can be appointed at cost if you prefer an independent report.
Tell us the scope. We will send the contract shape.
Send the site, the system size you have in mind and the country. We will reply with the right cooperation model, an outline programme and the payment schedule that fits it.