Process & contracting

From enquiry to handover — in writing.

Seven stages, six ways to contract, and a payment schedule you can see before you sign. No stage starts on a verbal instruction.

Delivery

Seven stages. One programme.

We can take the whole chain or a single stage. Either way, the sequence is planned before mobilisation, and the interface with your team is written down.

00

Survey

Roof or land, access, shading, structure, grid and load.

01

Design

Layout, yield, structural and electrical design, grid interface.

02

Supply

Specification, factory audit, pre-shipment inspection.

03

Logistics

Packing, shipping documents, customs coordination.

04

Construct

Mounting, modules, DC/AC, communications, safety systems.

05

Energise

Testing, commissioning, monitoring and grid acceptance.

06

Operate

Inspection, cleaning, spares, remote monitoring, training.

Cooperation models

Six ways to work with us.

Most first projects start as supply-only or supply-and-install, then grow into full EPC. The contract is sized to the scope you actually want.

ModelYou provideWe provideSuits
Design onlySite data, consumption, local grid rules.Layout, structural and electrical design, BoM, yield model.Owners with a local installer already selected.
Supply onlyApproved design and BoM.Equipment, inspection, documents, delivery to port or site.EPCs and installers who buy their own materials.
Design + supplySite access and approvals.Full design package plus equipment and logistics.Owners using a local installation contractor.
Supply + installSite access, permits, local labour support as agreed.Materials, our supervision crew, installation, commissioning.The most common first overseas model.
Full EPCLand or roof rights, permits, grid application, finance.Design, supply, construction, commissioning, handover pack.Owners who want one interface and one price.
EPC + O&MSite access and agreed reporting interface.Everything in EPC, plus inspection, cleaning, fault response and monitoring.Assets without a local O&M team.

Labour-only installation for a local EPC is also possible, quoted per kW or per day. Ask if that is what you need.

The agreement

What is actually in the contract.

We use a fixed-price contract with annexes, not a letter of intent followed by arguments. Every annex has an owner, a number and a date.

  • Scope & drawings annex. What is built, what is excluded, and the drawing revision the price is based on.
  • Bill of materials. Make, model, quantity and datasheet for every line.
  • Programme & milestones. Start, delivery, commissioning and acceptance dates with dependencies.
  • Price & payment schedule. Fixed price, currency, milestone payments, retention and release conditions.
  • Warranty & defects liability. Equipment warranty passed through; workmanship period stated in months.
  • Change orders, HSE, acceptance and dispute resolution. All written, all signed, all before work starts.

Templates available

We can start from our standard template or work under yours if it is balanced. Ask for the current set:

  • Supply contract — Incoterms 2020, inspection, title and risk
  • Installation contract — measured scope, site conditions, HSE
  • Full EPC contract — design, supply, install, commissioning
  • O&M agreement — service levels, response times, reporting

Request the templates

Money

Payment milestones, before you sign.

Payment is released against documents and completed work, not against promises. The percentages below are our standard; they can be adjusted with the scope and the country risk.

Equipment supply (T/T)

MilestoneShareReleased against
Order confirmation30%Signed contract and factory order placed.
Before shipment60%Pre-shipment inspection report, packing list, copy B/L.
After arrival10%Site or port acceptance of the delivered goods.

Installation / full EPC

MilestoneShareReleased against
Mobilisation20%Contract signed, site access and permits confirmed.
Delivery to site50%Equipment delivered and accepted, progress report signed.
Commissioning25%System energised, test records and as-builts issued.
Retention5%Released after the defects liability period, typically 12 months.
Also stated in the contract: currency (USD or CNY), bank charges, L/C at sight for first large orders, late-payment interest, and the treatment of taxes and duties under the chosen Incoterm. We do not offer unsecured credit terms.
After signature

What happens next, and who does it.

You get a named project manager and a single email thread. The sequence below is the standard path; dates are fixed at kickoff against your site.

  1. 01

    Kickoff and document freeze

    Scope, drawing revision, BoM and programme are frozen. Your contact and ours are named, with a weekly call slot.

    Output: signed kickoff record
  2. 02

    Design and approvals

    Layout, structural and electrical drawings issued for your approval. Local permits and grid application run in parallel on your side.

    Output: approved drawing set
  3. 03

    Factory order and inspection

    Purchase orders placed, hold points agreed, pre-shipment inspection witnessed or reported with photos.

    Output: PSI report and certificates
  4. 04

    Shipping and customs

    Consolidated shipment, documents issued, destination clearance coordinated with your broker.

    Output: B/L, CO, insurance, packing list
  5. 05

    Mobilisation and installation

    Crew, tools and materials on site. Daily progress photos, weekly report, safety induction completed.

    Output: weekly progress reports
  6. 06

    Commissioning and handover

    Testing, monitoring setup, operator training and the handover pack. Defects liability starts at acceptance.

    Output: commissioning report, as-builts, warranty pack
Site entry

What we need from you before mobilisation.

These are the items that most often delay a start. We check them at kickoff and confirm them again one week before the crew travels.

ItemWhy it mattersOwner
Site access and laydown areaCrane and truck access, secure storage for modules and steel.You
Power and waterTools, testing and concrete if foundations are in scope.You
Permits and grid applicationInstallation cannot be energised without them.You, with our technical inputs
Local labour and visasSome countries require a local hiring ratio; we plan the crew mix accordingly.Shared
HSE induction and site rulesOur crew works to your site rules and our own safety plan.You
Storage and accommodationRemote sites need secure container storage and crew lodging.Shared
Single point of contactOne person who can approve drawings and access without a committee.You
Questions

Before you ask.

Who stamps the drawings?

Design is issued and stamped by our partner design institutes in China. For local permits, the drawings may need review or re-stamping by a licensed engineer in your country; we prepare the package so that review is straightforward, and we can work with your local engineer.

Can I buy only the materials?

Yes. Send your approved BoM and we price it as supply-only, delivered FOB, CIF, DAP or DDP depending on what your customs setup allows.

What warranty do I get?

Equipment warranty is passed through from the manufacturer, typically 10–12 years product and 25–30 years performance for modules, and 5–10 years for inverters. Workmanship is warranted by Kunran for a stated period, typically 12–24 months. Exact terms are written into the contract, not assumed.

Who handles customs and duties?

We can quote DAP or DDP, but DDP requires a local entity or a trusted broker in your country. On first projects we usually recommend CIF or DAP with your broker clearing, so responsibility is clear on both sides.

Do you provide financing?

No. We can introduce you to banks and export credit insurers, but we do not lend and we do not take equity in projects.

What if you have never worked in my country?

Then we say so. For a first project in a new country we usually start with supply, or supply plus a supervision crew working alongside a licensed local installer. That keeps the regulatory risk with the party that holds the licence while you test how we work.

Can I visit the factory or witness inspection?

Yes. Factory visits and pre-shipment inspection can be arranged, and a third party such as BV or SGS can be appointed at cost if you prefer an independent report.

PV array on hillside terrain
Start here

Tell us the scope. We will send the contract shape.

Send the site, the system size you have in mind and the country. We will reply with the right cooperation model, an outline programme and the payment schedule that fits it.